5.2 Building Permit Application

Purpose

The purpose of this SOP is to outline the standardized process for submitting a building permit application in Mecklenburg County. It ensures that all required forms, documents, and steps are correctly completed and uploaded to the EPM system for review and approval, avoiding delays or rejections in the construction approval process.

Step 1: Access Required Forms

Review and access the necessary documentation using the following links:

Step 2: Log In and Begin Application

  1. Go to the EPM Portal.
  2. Click on Submit Building Construction Plan Application.
  3. Download the appropriate application form based on project type:
    • OnSchedule
    • Preliminary
    • RTAP

Step 3: Complete and Upload Application

Fill out the application completely, attach all required documents, and upload them to the EPM system for submission.

Step 4: Accept Review Date

After submission, confirm and accept the assigned review date as indicated by the EPM portal.

Step 5: Verify Submission Checklist

Ensure that all checklist items are completed before final submission:

  • ☐ Sheet Index — Download from EPM Forms
  • ☐ Address Verification Form — Download from EPM Forms
  • ☐ LOA (Letter of Authorization) to pay for permit fees
  • ☐ Bookmarked Drawings
  • ☐ Building Permit Application