Who handles the permit
Mecklenburg County Code Enforcement coordinates commercial plan review and permits for the City of Charlotte, the towns of Cornelius, Davidson, Huntersville, Matthews, Mint Hill and Pineville, and the County. Zoning is handled separately by the planning office for the property. A tenant upfit usually needs both to agree: the zoning office confirms the use is allowed, and Code Enforcement reviews the drawings against the North Carolina State Building Code.
The review options
The County offers several ways to have commercial plans reviewed. Two matter most for tenant work:
- Express OnSchedule. According to the County, it covers tenant upfits, interior alterations and change of use permits, along with certain categories of new construction, and it is designed to move review from weeks to a single review session.
- Small Commercial review. The County’s page describes accepting interior upfits for business and mercantile occupancies up to 10,000 SF, with exclusions. Eligibility depends on the project, so check the page and ask the County.
Larger or more complex projects go through standard plan review. Review rules and programs change, so confirm the current options with the County before you plan your schedule around one.
What to prepare
A reviewer works from drawings, so a complete set is the most useful thing a tenant can bring:
- Floor plans showing walls, doors, rooms and exits.
- Reflected ceiling plan and lighting.
- Mechanical, electrical and plumbing drawings from the engineers.
- Life safety information such as exits, occupant load and restrooms.
- The use of the space and the square footage.
Mecklenburg County’s own example shows why use matters: a business occupancy is calculated at 100 square feet per person for exit requirements, so a 3,000 SF space has an occupant load of 30, and a change of use can change that.
Where it fits in the schedule
For an office of about 4,000 SF, our planning model runs about six months from the start of design to move-in, with a few weeks of permitting between design and construction. Read the whole sequence in our guide to office renovation in Charlotte.
When the use changes
If the upfit changes the way the space is used, for example an office that becomes a clinic, more review applies. Our guide to change of use in Mecklenburg County explains the steps, and our change of use architecture service covers the design.
What to confirm with the County
Rules, thresholds and review times change, and this article is not a substitute for the reviewing authority. Before you rely on any of it, confirm with Mecklenburg County Code Enforcement which review option fits your project, which version of the State Building Code applies and whether zoning needs separate approval.
What to bring to a first conversation
The address, the square footage, the existing and the proposed use and any drawings you have. Contact the studio or read about our commercial interior design services.